Session 4 (Implementation Planning) has completed comprehensive 4-week sprint planning: Deliverables: - Week 1-4 detailed schedules (162 total hours) - 24 API endpoints (OpenAPI 3.0 specification) - 5 database migrations (100% rollback coverage) - Testing strategy (70% unit, 50% integration, 10 E2E flows) - 28 Gherkin acceptance criteria scenarios - Dependency graph with critical path analysis - Zero-downtime deployment runbook Agents: S4-H01 through S4-H10 (all complete) Token Cost: $2.66 (82% under $15 budget) Efficiency: 82% Haiku delegation Status: Ready for Week 1 implementation kickoff
136 lines
5.9 KiB
JSON
136 lines
5.9 KiB
JSON
{
|
|
"performative": "inform",
|
|
"sender": "if://agent/session-4/S4-H07",
|
|
"receiver": ["if://agent/session-4/S4-H10"],
|
|
"conversation_id": "if://conversation/navidocs-session-4-critical-path-2025-11-13",
|
|
"content": {
|
|
"claim": "Critical path identified: 27 calendar days (18-19 work days) with 3-5 day slack buffer for blockers. Sequential execution required for solo developer. Foundation tasks (DB Migrations → Event Bus → Background Jobs) are hard blockers for all Week 2+ work.",
|
|
"evidence": [
|
|
"Detailed dependency analysis from CLOUD_SESSION_4_IMPLEMENTATION_PLANNING.md",
|
|
"576-line dependency graph document with 4 Mermaid Gantt charts",
|
|
"5 risk areas identified with mitigation strategies",
|
|
"4 weekly go/no-go gates defined",
|
|
"Parallel work opportunities quantified (6 days deferrable)"
|
|
],
|
|
"critical_path": "DB Migrations (Day 1) → Event Bus (Day 2) → Background Jobs (Day 5) → Warranty APIs (Days 7-9) → E2E Testing (Day 23) → Security Audit (Day 24) → Deployment (Days 25-27)",
|
|
"critical_path_duration_calendar_days": 27,
|
|
"critical_path_duration_work_days": "18-19",
|
|
"slack_time_available_days": 3.5,
|
|
"slack_percentage": "18%",
|
|
"risk_areas": [
|
|
{
|
|
"rank": 1,
|
|
"name": "Home Assistant Webhook Validation Unknown",
|
|
"impact": "1-2 day delay",
|
|
"probability": "medium",
|
|
"mitigation": "Spike on HA API requirements Day 9 PM (2-4 hours). Have fallback if unreachable."
|
|
},
|
|
{
|
|
"rank": 2,
|
|
"name": "OWASP Dependency Scan Failures",
|
|
"impact": "1-2 days delay",
|
|
"probability": "medium",
|
|
"mitigation": "Run audit baseline Day 1. Update dependencies early Week 1. Schedule audit Day 24 (not Day 27)."
|
|
},
|
|
{
|
|
"rank": 3,
|
|
"name": "Database Migration Edge Cases",
|
|
"impact": "0.5-1 day delay",
|
|
"probability": "medium",
|
|
"mitigation": "Test rollback immediately after Day 1. Validate SQLite foreign key behavior."
|
|
},
|
|
{
|
|
"rank": 4,
|
|
"name": "Playwright E2E Setup Complexity",
|
|
"impact": "0.5 day delay",
|
|
"probability": "low",
|
|
"mitigation": "Start E2E Day 22 (not Day 23). Use templates. Pre-build test cases."
|
|
},
|
|
{
|
|
"rank": 5,
|
|
"name": "Production Deployment Issues",
|
|
"impact": "2-4 hours + rollback",
|
|
"probability": "low",
|
|
"mitigation": "Full rehearsal Day 25 on staging. Automated smoke tests. Rollback drill."
|
|
}
|
|
],
|
|
"parallel_opportunities": [
|
|
{
|
|
"name": "Week 2: Warranty APIs + Home Assistant (Days 7-14)",
|
|
"sequential_time": "5d",
|
|
"parallel_time": "3d",
|
|
"days_saved": 1.5,
|
|
"requires": "2 developers"
|
|
},
|
|
{
|
|
"name": "Week 3: Sale Workflow + Notifications (Days 15-22)",
|
|
"sequential_time": "5d",
|
|
"parallel_time": "3d",
|
|
"days_saved": 1.5,
|
|
"requires": "2 developers"
|
|
},
|
|
{
|
|
"name": "Week 4: MLS Integration (Optional Deferral)",
|
|
"sequential_time": "3d",
|
|
"parallel_time": "defer",
|
|
"days_saved": 3,
|
|
"requires": "schedule slip handling"
|
|
}
|
|
],
|
|
"optional_features_deferral_order": [
|
|
"MQTT Integration (Day 10 afternoon) = +1 day slack",
|
|
"Camera Integration (Day 11 afternoon) = +1 day slack",
|
|
"MLS Integration (Days 23-26) = +3 days slack",
|
|
"Riviera Pilot Training (Days 27-29) = +1 day slack"
|
|
],
|
|
"weekly_gates": [
|
|
{
|
|
"week": 1,
|
|
"deadline": "2025-11-16T17:00:00Z",
|
|
"go_criteria": "DB migrations + Event Bus tested, Background Jobs registered, Week 1 acceptance 90%+ passing",
|
|
"no_go_criteria": "DB migrations unstable OR Event Bus failing tests"
|
|
},
|
|
{
|
|
"week": 2,
|
|
"deadline": "2025-11-23T17:00:00Z",
|
|
"go_criteria": "Warranty APIs stable, HA integration working, Integration tests 80%+ passing",
|
|
"no_go_criteria": "Warranty APIs failing tests OR HA webhook unreachable"
|
|
},
|
|
{
|
|
"week": 3,
|
|
"deadline": "2025-11-30T17:00:00Z",
|
|
"go_criteria": "Sale workflow complete, Notifications 90%+ done, Offline mode working, E2E skeleton ready",
|
|
"no_go_criteria": "Sale workflow failing OR notification system unreliable"
|
|
},
|
|
{
|
|
"week": 4,
|
|
"deadline": "2025-12-10T17:00:00Z",
|
|
"go_criteria": "All features deployed, E2E tests passing, Security audit passed, Post-deploy validation OK",
|
|
"no_go_criteria": "Post-deploy validation failing OR critical security issues found"
|
|
}
|
|
],
|
|
"key_bottlenecks": [
|
|
"DB Migrations Day 1 (zero slack - blocks everything)",
|
|
"Event Bus Day 2 (zero slack - blocks jobs + async)",
|
|
"Background Jobs Day 5 (zero slack - blocks notification flows)",
|
|
"Warranty APIs Days 7-9 (critical - foundation for Week 2+)",
|
|
"Security Audit Day 24 (gate for deployment)"
|
|
],
|
|
"recommendations_for_S4H10": [
|
|
"Deployment checklist should include pre-deployment 'dress rehearsal' on staging (Day 25)",
|
|
"Post-deployment validation (Day 27) is NOT optional - builds in 1-day contingency",
|
|
"Rollback procedure must be tested before production deploy",
|
|
"Monitor first 24 hours of production deployment actively (have developer on-call Dec 9)",
|
|
"Riviera pilot setup is optional - defer if deployment takes longer than expected"
|
|
],
|
|
"confidence": 0.92,
|
|
"confidence_rationale": "High confidence based on detailed task specifications in planning document. Medium confidence in HA integration (unknown requirements). Risk areas quantified and mitigated.",
|
|
"cost_tokens": 3847,
|
|
"timestamp": "2025-11-13T10:00:00Z",
|
|
"sequence_num": 1
|
|
},
|
|
"citation_ids": [
|
|
"file:///home/user/navidocs/CLOUD_SESSION_4_IMPLEMENTATION_PLANNING.md#dependency-graph-gantt-chart",
|
|
"file:///home/user/navidocs/intelligence/session-4/dependency-graph.md"
|
|
]
|
|
}
|